East Avenue Middle
East Avenue Middle School Renovation Project
Project Scope - Phase 1
- Installation of underground utilities.
- Building pad prep.
- Installation of a new exercise classroom.
Project Scope - Phase 2
- Demolition and relocation of existing relocatable classrooms, rough grading, and installation of underground utility lines.
- Construction of a new 24,000 square foot two-story classroom building. The building will have 16 classrooms as well as student and staff restrooms.
- Installation of underground utilities.
Project Scope - Phase 3
- Increment 3 - Renovation of the administrative building A, B-wing classrooms, and student courtyard.
Completed on schedule and within budget.